Track layout Rummelsburg
VGR track layout modification Rummelsburg, construction work main measure
Client
DB Netz AG, East Regional Division
Project volume
EUR 36.0 million (approx.)
Construction time
05/2016 – 06/2019 (38 months)
Conversion of the track layout of the Rummelsburg station in 3 main construction phases during railway operations; includes civil engineering underground work, demolition of buildings, construction of processing platforms and new construction of a pedestrian underpass as well as approx. 7,500 m of track and point conversion work during lockouts, including associated equipment and fitting work.
- approx. 7,950 m of track dismantling incl. 62 sets of points
- approx. 7,500 m of new track construction incl. 45 sets of points
- approx. 93,000 t of excavated soil
- approx. 5,000 m of drainage pipes and sewer with storage capacity and overflow
- approx. 40,000 t of ballast installed
- New construction of 3 retain walls and 1 noise barrier
- New construction of 3 processing platforms incl. equipment and fittings
- 5,300 m of cable ducts constructed and approx. 103,000 m of cables
- approx. 3,500 m of fire water and compressed air lines constructed
- Demolition and disposal of 2 administration buildings and one car hall
- Reconstruction and new construction of technical equipment: Overhead contact line system, point heating systems, lighting systems, train preheating system