Track layout Rummelsburg

VGR track layout modification Rummelsburg, construction work main measure

Rummelsburg(1)

Client

DB Netz AG, East Regional Division

Project volume

EUR 36.0 million (approx.)

Construction time

05/2016 – 06/2019 (38 months)

Conversion of the track layout of the Rummelsburg station in 3 main construction phases during railway operations; includes civil engineering underground work, demolition of buildings, construction of processing platforms and new construction of a pedestrian underpass as well as approx. 7,500 m of track and point conversion work during lockouts, including associated equipment and fitting work.

 

  • approx. 7,950 m of track dismantling incl. 62 sets of points
  • approx. 7,500 m of new track construction incl. 45 sets of points
  • approx. 93,000 t of excavated soil
  • approx. 5,000 m of drainage pipes and sewer with storage capacity and overflow
  • approx. 40,000 t of ballast installed
  • New construction of 3 retain walls and 1 noise barrier
  • New construction of 3 processing platforms incl. equipment and fittings
  • 5,300 m of cable ducts constructed and approx. 103,000 m of cables
  • approx. 3,500 m of fire water and compressed air lines constructed
  • Demolition and disposal of 2 administration buildings and one car hall
  • Reconstruction and new construction of technical equipment: Overhead contact line system, point heating systems, lighting systems, train preheating system