Oberhausen-Emmerich BA 1
The project consists of a 3 km long section of the continuous three-track extension of line 2270 (ABS) 46/2 (Amsterdam-) border D/NL - Emmerich-Oberhausen
Client
DB AG, Duisburg
Project volume
EUR 33,7 million
Construction time
05/2019 - 03/2027 (95 month)
In the inner-city area of Oberhausen, the route will be widened during closure periods with approx. 100,000 m³ of earthworks, 5,000 m of track an 8 switches, as well as 2,500 m of bored piles and 7,000 m of vibrated stone columns. In addition to the associated civil engineering, waste diposal, drainage and underground cable works, construction work ist being carried out on 9 engineering structures and catenary work on 3,000 m of track with 140 new masts.
Services:
- Earth movement
- Drainage DN 150 - 400
- Cable civil engineering
- Track construction
- Civil engineering structures
- Special civil engineering
- Catenary
- Execution planning of the traffic and catenary system