Nikolaus-Dürkopp-Straße, Bielefeld

Drainage, track and road construction work in the Nikolaus-Dürkopp-Straße, reconstruction of the Niederwall triangular rail node and production of a mass-spring system in the intersection area Nikolaus-Dürkopp-Straße / August-Bebel-Straße in Bielefeld.

Nikolaus-Dürkopp-Str.(4)

Client

Bielefelder Beteiligungs- und Vermögensverwaltungsgesellschaft

Project volume

EUR 2.1 million

Construction time

06/2015 – 01/2016 (8 months)

Drainage, track and road construction work in the Nikolaus-Dürkopp-Straße, reconstruction of the Niederwall triangular rail junction and production of a mass-spring system in the intersection area Nikolaus-Dürkopp-Straße / August-Bebel-Straße in Bielefeld.
 

  • Traffic safety, waste disposal services, surveying work for track and road construction as well as preparation of as-built plans
  • 1,240 + 5,705 m³/m² of soil excavation / removal (partly for disposal on landfill)
  • 2,665 m³ of shoring (vertical trench shoring with chamber slabs with trench sheets and load-bearing shoring of end walls)
  • 680 m of sewerage duct installed, including branching and connection pieces (DN 160–600)
  • 50 m of building connection pipes restored
  • 2,230 m² of paved areas renewed (paving stones and slabs)
  • 1,030 m of kerbstones installed/laid
  • 950 m of paving guttering installed/laid
  • 6,760 m² / 135 t of (poured) asphalt installed (incl. slab track area)
  • 825 m of grooved rail track produced, incl. sheathing and sub-casting
  • 3 x grooved rail points installed/laid
  • 1 x installation of grooved rail crossing
  • 115 m of Vignole rail track produced
  • 2 x core Vignole point renewed 
  • 1 x installation of Vignole rail crossing
  • 100 m of mass-spring system produced, incl. base layers and sub-cast (incl. concrete work)
  • 288 x welding productions