New construction Emscherbrücken rail overpass

New construction of two railway overpasses over the Emscher in Oberhausen as part of the Betuwe Line.
Extension of the three existing lines by two additional lines.

Emscherbrücke_1

Client

DB Netz AG, Duisburg

Project volume

EUR 6,7 million

Construction time

04/2018 - 05/2020 (25 month)

Services

Companies

  • Roßlauer Schiffswerft

 

 

  • Construction of four concrete abutments on bored piles
  • Construction of two truss bridges
  • Special civil engineering work from shoring an bored pile work
  • Superstructure and track construction work
  • Disposal and demolition of a gas pipeline bridge