Forchheim-Süd track construction
VDE 8.1.1 Nuremberg–Ebensfeld VP 18,500 Forchheim–Süd line extension, km 31.2–39.7
![Forchheim](/sites/wittfeld/files/styles/header_image_small/public/content/images/project/2018-06/Arge_Forchheim_1%5B1%5D_1.jpg?itok=iFEqIilK)
Client
DB Netz AG, Projektzentrum Nürnberg
Project volume
EUR 116.9 million (approx.)
Construction time
05/2016 – 07/2019 (39 months)
Extension of the existing dual-track line from km 31.2–39.7 to 4 tracks between the Baiersdorf stop and the Forchheim railway station, as well as reconstruction of the existing line, detour lines during interruptions in line closures.
- Construction of 7 railway bridges and 1 road overpass
- Reconstruction work on 5 road viaducts
- Reconstruction of Forchheim railway station with 3 platforms and pedestrian underpass
- New construction of a stop with pedestrian underpass
- 36,000 m of track work and 35 sets of points
- approx. 750,000 m³ of earthworks
- approx. 1,300 m of retaining walls and 50,000 m² of noise barriers
- approx. 21,000 m of underground cabling
- Technical equipping overhead lines, TK, LST
![](/sites/wittfeld/files/styles/image_grid_portrait_small/public/content/images/2018-06/Arge_Forchheim_2%5B1%5D.jpg?itok=bIXwLPiS)
![](/sites/wittfeld/files/styles/image_grid_landscape_small/public/content/images/2018-06/Arge_Forchheim_3%5B1%5D.jpg?itok=55WQk1-g)
![](/sites/wittfeld/files/styles/image_grid_landscape_small/public/content/images/2018-06/Arge_Forchheim_4%5B1%5D.jpg?itok=3R-2G2I9)