380_KV-Overhead Line Emden-Ost - Conneforde, Lot 2
New construction of the 380 kV-overhead line Emden-Ost - Conneforde, Lot 2
Client
Eiffage Energie Transport & Distribution (TenneT)
Project volume:
EUR 7.5 million
Construction time
03/2020 - 01/2022 (22 month)
Services
- Light site access roads
- Heavy access roads
- Assembling of 5 auxiliary bridges
- Pylon foundation on bored piles
- Dismantling of foundations of existing lines
- Ballast
- Open dewatering